Level Crossing Work 5

Cold January mornings give everything a glistening sheen of frost.

IMG_8034

IMG_8020

A couple of pics showing level crossing construction progress.

Stone setts kept with new parking bays to the right

Stone setts kept with new parking bays to the right

Concrete complete - Almost unrecognisable from the scene a year ago!

Concrete complete – Almost unrecognisable from the scene a year ago!

 

The two steam locos were outside the shed this morning, Portbury was having her fire lit.

Level Crossing Work 4

The concrete has now been poured for the level crossing.

As mentioned previously, this area was relaid with concrete sleepers as wooden ones do degrade and can rot over time. Next we should be seeing work done on the approaches, and the laying of the roadway around the back of the shed.

Level Crossing Work 2

Both lines have now been lifted, and the trackbed excavated.