Track lifting is well under way at Butterfly Junction, just the pointwork rails and the sleepers remaining in the station area. These photos also show the vegetation clearance that has taken place.

Ashton Avenue Bridge is now closed for refurbishment, along with the former trackbed. No doubt the rails still on the bridge will be coming out shortly.

A different scene over at SS Great Britain Halt, where the buffer stop has been moved from the end of the line here. I believe that this is to be used as the basis for a small shed, which should come in useful if the branch along the New Cut is closed while MetroBus is under construction.

Level Crossing Work 5

Cold January mornings give everything a glistening sheen of frost.

IMG_8034

IMG_8020

A couple of pics showing level crossing construction progress.

Stone setts kept with new parking bays to the right

Stone setts kept with new parking bays to the right

Concrete complete - Almost unrecognisable from the scene a year ago!

Concrete complete – Almost unrecognisable from the scene a year ago!

 

The two steam locos were outside the shed this morning, Portbury was having her fire lit.

Level Crossing Work 2

Both lines have now been lifted, and the trackbed excavated.

Whapping Wharf Building work update – March 2014

Work is forging ahead next door to M Shed, on the Wapping Wharf housing scheme. This includes the resurfacing of the square outside the engine shed, seen here:

IMG_3416

The disused loop line has been cut into for drainage.

IMG_3418

This scene is soon to change drastically, with the roadway being taken alongside the running line, to a new level crossing just out of sight.

IMG_3419

‘Container city’ on the right.

IMG_3422