We’re Going Back up the Branch! (II)

Thankfully we have been lucky with the weather recently and have done more work on repairing and rebuilding the branch to A Bond.

EVEN MORE concrete sleepers have arrived and were stashed on wagons. These deliveries have almost finished now with enough in stock to relay the majority of the running line. Bob caught these photos of Crane 32 doing the honours with Henbury ready to tow them away.

A thankless task has been moving the stacks of concrete sleepers which were left on the trackbed in the new station area. The contractors employed to fix the wall of the New Cut and the Chocolate Path were meant to have installed these in ‘the gap’ but for some reason this was not done before the work site was cleared. We need to re-grade this area due to the height difference in the old running line and the new yard area, so the laborious work of moving all the sleepers had to be done by Larry and a few volunteers. Frustrating, but necessary to allow work to continue.
Chris cleared the last few earlier last week leaving the platform road clear.

At the weekend we were then able to drag another 30-foot rail into position at the railhead and begin to hammer keys into every other rail chair to give the track some rigidity. Then, using a turfer ratchet chain thingy we slewed the 60-foot panel to begin making a gently curve towards the station.
The view at the end of the day shows the new curve as well as the height discrepancy between the new track and the old. The old railhead will need jacking up and re-packing underneath once it’s been connected to the new panel.

Bringing Back the Branch

A few blog posts recently have covered the acquisition of loads of second-hand concrete sleepers. This is all in aid of bringing the New Cut branch back in to use.
It’ll soon be 10 years since the track was lifted at Butterfly Junction to make way for the Metrobus Guided Busway.

The return was delayed as in early 2020, the ongoing subsidence of the New Cut wall came to a head as the wall, the Chocolate Path and the Railway all collapsed into the Cut.


The wall has since been fixed, but then came the refurbishment of Vauxhall Bridge (halfway down the branch) which requires a large amount of scaffolding blocking the track.

The current railhead at the new section of wall, with a fenced-off Vauxhall Bridge in the background.

The aim is to be ready to commence tracklaying and sleeper replacement as soon as possible, to return trains to the station at ‘A’ Bond warehouse.
To this end, volunteers and staff, along with Larry the trusty loader, have been working down at A Bond to position the platform and track, sort through the materials and work out what is re-usable and what needs refurbishment. Hauling track out of the undergrowth is part of the challenge!
The platform has been shot-blasted and repainted to protect it.
Thanks to Chris and Katie for these photos.

Hopefully this work shows a statement of intent to the public that the branch is on its way back.

Back on the Wharf, a huge amount of hedge trimming and lineside clearance has taken place along the curve to Cumberland Road Bridge, requiring use of the Coles Crane and cage, seen here returning to the shed at the end of a running day.

The next step was the clearance of the ash pile next to the pit, which was getting rather tall. This required use of the grab and the Vincent wagon. The ashes are being used to create a walking route for trackworkers and shunters alongside the running line, where there was previously very limited clearance. Ash paths were a staple of the steam-era railway environment as there was so much of it around. More sorting and moving of sleepers and chairs was also done. The crane’s new clear acrylic roof and windscreen are very useful for this work.

More to come as work progresses….

Brake Van Rides with Pannier 1369 – 1 day only!

If you’d like the chance to ride behind GWR Pannier Tank No. 1369 on the Bristol Harbour Railway, there will be a one-time chance to do so.
To celebrate RAIL200, on Friday 14th March 2025, 1369 will be running short trips with the newly-outshopped Toad Brake Van up to Vauxhall Bridge and back on the branch. There may be the opportunity to dismount at Vauxhall Bridge and take photos.
Places are limited to 10 people per trip and the price is £10 per person for 1 round trip (cash or card, payable on the day).
Spaces are on a first-come, first-serve basis on the day and the first trip will be at 11am. There will be approximately 4 trips on the day (depending on demand and staffing).
1369 will be returning to the South Devon Railway soon so this may be the only chance to travel behind it and a rare opportunity to ride on the New Cut Branch.
Please note that as the Toad is the only passenger vehicle on this service, it will be difficult to provide wheelchair access due to the width of the doors.